China's first offshore oilfield group energy storage power station, full capacity grid connection

2023-09-22 09:24:44

It consists of two sets of 2.5 MW air-cooled energy storage systems with a total of 11200 batteries, a single container weight of about 56 tons, and a total storage capacity of 10000 kilowatt-hour.

"The self-check of the energy storage device is passed, and the grid connection procedure is started".

"The first switch is switched successfully, and the grid connection is successfully completed!" With the issuance of instructions, the data on the large screen in the control room of Weizhou Terminal Energy Storage Power Station moved up, and the continuous current was transmitted to the offshore oil field group power grid through the energy storage device

.

On September 20, the full capacity of China's first energy storage power station applied to the offshore oilfield group power grid was integrated into the southwest oilfield group power grid. The energy storage power station is located in the terminal treatment plant of Weizhou Island, Beihai City, Guangxi, CNOOC, covering an area of about 500 square meters.

The power station consists of two sets of 2.5 MW air-cooled energy storage systems with a total of 11200 batteries, a single container weight of about 56 tons, and a total energy storage capacity of 10000 kilowatt-hour . After the energy

storage power station is put into operation, the power grid of Southwest Oilfield Group will consist of five gas-fired power stations, one waste heat power station, one photovoltaic power station and one energy storage power station. The total installed capacity is 112 MW, which shoulders the important task of supplying power for oil and gas production in Southwest Oilfield Group and people's livelihood and tourism in Weizhou Island. The energy storage power station

put into operation this time consists of two sets of 2.5 MW-2 hours air-cooled energy storage systems in parallel. From the outside, they are four white container-like cubes, each consisting of a battery container and a converter booster system. Gao Chuanlian, the

project leader, said that the battery of the energy storage power station uses the current mainstream lithium iron phosphate single battery, and the battery container is similar to a "power bank", which is responsible for power storage. Each battery can store 5000 kWh of electricity; The direct current released by the battery is converted into 35 kilovolt alternating current matched with the power grid through the converter and booster integrated machine, which is integrated into the power grid.


All can be viewed after purchase
Correlation

One has been established for five years and one for 17 years.

2026-09-07 09:17:48

What is happening in the cement industry?

2026-09-06 07:02:03

Some second and third-tier enterprises have taken the lead in reducing prices slightly.

2026-09-04 16:36:43

Domestic concrete price statistics in August showed that the national concrete price fell by 1.16% annually and 6.51% year-on-year. Prices in most areas have changed to varying degrees. On a month-on-month basis, prices in some regions changed significantly, such as Shanghai and Sichuan, where the decline was relatively large, while prices in Beijing, Shanxi and Inner Mongolia remained unchanged on a month-on-month basis. On a year-on-year basis, the decline in Jilin is relatively prominent, while Shanxi has a small increase over the same period. Overall, the domestic concrete price showed a certain fluctuation trend in August.

2026-09-01 11:18:22

The proportion of photovoltaic power generation in the electricity consumption of the whole society has reached 13%, and more than one kilowatt-hour of electricity used in the whole country comes from photovoltaic power.

2026-09-01 11:12:19

For the first time, the installed capacity of photovoltaic power generation exceeded that of coal-fired power generation, making it the largest power supply category in China.

2026-09-01 10:48:28

Nandian (Chengmai) New Energy Technology Co., Ltd. is not the first time to be listed for transfer. According to the tracking of the Digital New Energy DataBM. Com, the target was listed on the Beijing Property Exchange on July 21, 2026, and the transfer base price at that time was 86.45 million yuan.

2026-08-26 11:36:03

From January to July this year, the newly installed photovoltaic capacity in China was 86.15GW, down 61.41% from the same period last year.

2026-08-25 11:39:44

Dongfang Tiansuan signed a cooperation agreement with the State Inspection Group, and the two sides will jointly build a "Space Photovoltaic Joint Laboratory" to carry out joint research on space photovoltaic materials, satellite-borne photovoltaic cells/components, space environment reliability, testing methods, standard system and on-orbit verification.

2026-08-22 16:19:40

The shortage of transformers is becoming the hidden ceiling of new energy grid connection. For the photovoltaic industry, the lag of grid infrastructure has been the biggest obstacle to consumption; when the grid investment is really accelerated, the grid-connected space of new energy such as photovoltaic will also be opened.

2026-08-21 13:07:15

In the third quarter, the grid-connected capacity of distributed photovoltaic in all counties (cities and districts) of Guangdong Province was 24.210 GW.

2026-08-20 13:05:01

Seven manufacturers, including Jingke Energy, Trina Solar Energy, Jingao Technology, Atlas, Dongfang Risheng, Yingli Energy and Runma Solar Energy, raised their component quotations by 0.01-0.03 yuan/W.

2026-08-12 17:50:55

On July 29, Longji Green Energy released the pre-approval announcement of the environmental impact assessment of the new crystalline silicon-perovskite tandem solar cell technology and equipment industrialization project and the new high-efficiency back contact (BC) cell technology and equipment project of Xixian New Area Branch.

2026-08-12 16:36:35

It is worth noting that the meeting not only formed a consensus on self-discipline among enterprises, but also put forward a series of supporting disciplinary measures and suggestions:

2026-08-07 14:24:19

On July 30, the Hunan Development and Reform Commission held the second comprehensive roadshow of major projects in the province in 2026. Among them, Yanhe Intelligent Perovskite New Material Production Line Project was unveiled.

2026-08-06 09:07:52

Although the quotation side continues to weaken, the demand side of the distributed market has shown a phased recovery.

2026-08-05 15:52:42

The Plan rationally arranges the construction scale of various power sources, power grids and regulating resources, and optimizes the technical routes and spatial layout of pumped storage and new energy storage. By 2030, the installed capacity of new energy storage will reach 300 million kilowatts, and the interaction between vehicles and networks will strive to reach about 50 million kilowatts, so as to reduce the cost of power system transformation and the cost of electricity consumption in the whole society.

2026-08-05 10:21:33