False Report, Illegal Land Occupation, Datang 2 Million Kilowatt Scenery Project Notified

2023-09-18 09:44:16

At the same time, the project also has illegal acts of destroying forest land, and the circumstances are serious.

Digital New Energy DataBM. Com received a circular on September 14 from the Forestry and Grassland Administration of Inner Mongolia Autonomous Region and the Energy Bureau of Inner Mongolia Autonomous Region on the application procedures for the use of forest land for the 2 million kilowatt wind and solar power project (Datang Qingshuihe Wind Power Project).

After verification, in order to avoid the relevant requirements for examination and approval, some plots in the Feasibility Report on the Use of Forest Land of this project are inconsistent with the existing land, and there are fraudulent acts. At the same time, the project also has illegal acts of destroying forest land, and the circumstances are serious.

The original text is as follows:

Inner Mongolia Autonomous Region Forestry and Grassland Bureau Autonomous Region Energy Bureau on Mengxi Tuoketuo Wind Power Project (Datang Qingshui River Wind Power Project)

Inner Mongolia Datang International Tuoketuo Power Generation Co., Ltd.:

The Forestry and Grass Bureau of the Autonomous Region found in the review of your company's application for the use of forest components for the "Mengxi Tuoketuo 2 million kilowatt wind and solar power project (Datang Qingshuihe Wind Power Project)". There are suspected false problems in the Feasibility Report on the Use of Forest Land. To this end, the Forestry and Grass Bureau of the Autonomous Region organized personnel to conduct on-site investigation and verification. After verification, in order to avoid the relevant requirements for examination and approval, some plots in the Feasibility Report on the Use of Forest Land of this project are inconsistent with the existing land, and there are fraudulent acts . At the same time, the project also has illegal acts of destroying forest land, and the circumstances are serious. In strict accordance with the Management Standards for Examination and Approval of Forest Land Use in Construction Projects, your company

is requested to pay close attention to rectification, actively cooperate with the local forestry and grass departments to hand over the illegal problems to the public security organs for investigation and punishment, correct the false contents in the components, and re-report as soon as possible. The Forestry and Grassland Administration of

the Autonomous Region has listed Inner Mongolia Mengeli Engineering Project Management Co., Ltd., which compiled the Feasibility Report on the Use of Forest Land, in the list of bad credit records, and the forestry and grassland departments at all levels will no longer accept the Feasibility Report on the Use of Forest Land and the Questionnaire on the Status of the Use of Forest Land.

Inner Mongolia Datang International Tuoketuo Power Generation Co., Ltd. is a key enterprise in the autonomous region. It has played an important role in the economic and social development of the autonomous region and is the mainstay of the national economy in our region. However, it should also operate and manage in accordance with the law, consciously abide by laws and regulations, and operate in good faith. At the same time, your company should take active actions to strengthen the supervision and management of Datang Qingshuihe New Energy Co., Ltd., a wholly-owned subsidiary, enhance the overall situation awareness, consciously improve the ability and level of operation and management according to law, and play an exemplary role in standardizing the order of socialist market economy, maintaining and promoting fair competition in the market.

Hereby notify. August 25

,

2023

All can be viewed after purchase
Correlation

One has been established for five years and one for 17 years.

2026-09-07 09:17:48

What is happening in the cement industry?

2026-09-06 07:02:03

Some second and third-tier enterprises have taken the lead in reducing prices slightly.

2026-09-04 16:36:43

Domestic concrete price statistics in August showed that the national concrete price fell by 1.16% annually and 6.51% year-on-year. Prices in most areas have changed to varying degrees. On a month-on-month basis, prices in some regions changed significantly, such as Shanghai and Sichuan, where the decline was relatively large, while prices in Beijing, Shanxi and Inner Mongolia remained unchanged on a month-on-month basis. On a year-on-year basis, the decline in Jilin is relatively prominent, while Shanxi has a small increase over the same period. Overall, the domestic concrete price showed a certain fluctuation trend in August.

2026-09-01 11:18:22

The proportion of photovoltaic power generation in the electricity consumption of the whole society has reached 13%, and more than one kilowatt-hour of electricity used in the whole country comes from photovoltaic power.

2026-09-01 11:12:19

For the first time, the installed capacity of photovoltaic power generation exceeded that of coal-fired power generation, making it the largest power supply category in China.

2026-09-01 10:48:28

Nandian (Chengmai) New Energy Technology Co., Ltd. is not the first time to be listed for transfer. According to the tracking of the Digital New Energy DataBM. Com, the target was listed on the Beijing Property Exchange on July 21, 2026, and the transfer base price at that time was 86.45 million yuan.

2026-08-26 11:36:03

From January to July this year, the newly installed photovoltaic capacity in China was 86.15GW, down 61.41% from the same period last year.

2026-08-25 11:39:44

Dongfang Tiansuan signed a cooperation agreement with the State Inspection Group, and the two sides will jointly build a "Space Photovoltaic Joint Laboratory" to carry out joint research on space photovoltaic materials, satellite-borne photovoltaic cells/components, space environment reliability, testing methods, standard system and on-orbit verification.

2026-08-22 16:19:40

The shortage of transformers is becoming the hidden ceiling of new energy grid connection. For the photovoltaic industry, the lag of grid infrastructure has been the biggest obstacle to consumption; when the grid investment is really accelerated, the grid-connected space of new energy such as photovoltaic will also be opened.

2026-08-21 13:07:15

In the third quarter, the grid-connected capacity of distributed photovoltaic in all counties (cities and districts) of Guangdong Province was 24.210 GW.

2026-08-20 13:05:01

Seven manufacturers, including Jingke Energy, Trina Solar Energy, Jingao Technology, Atlas, Dongfang Risheng, Yingli Energy and Runma Solar Energy, raised their component quotations by 0.01-0.03 yuan/W.

2026-08-12 17:50:55

On July 29, Longji Green Energy released the pre-approval announcement of the environmental impact assessment of the new crystalline silicon-perovskite tandem solar cell technology and equipment industrialization project and the new high-efficiency back contact (BC) cell technology and equipment project of Xixian New Area Branch.

2026-08-12 16:36:35

It is worth noting that the meeting not only formed a consensus on self-discipline among enterprises, but also put forward a series of supporting disciplinary measures and suggestions:

2026-08-07 14:24:19

On July 30, the Hunan Development and Reform Commission held the second comprehensive roadshow of major projects in the province in 2026. Among them, Yanhe Intelligent Perovskite New Material Production Line Project was unveiled.

2026-08-06 09:07:52

Although the quotation side continues to weaken, the demand side of the distributed market has shown a phased recovery.

2026-08-05 15:52:42

The Plan rationally arranges the construction scale of various power sources, power grids and regulating resources, and optimizes the technical routes and spatial layout of pumped storage and new energy storage. By 2030, the installed capacity of new energy storage will reach 300 million kilowatts, and the interaction between vehicles and networks will strive to reach about 50 million kilowatts, so as to reduce the cost of power system transformation and the cost of electricity consumption in the whole society.

2026-08-05 10:21:33