On December 25, the Heilongjiang Development and Reform Commission issued an announcement on the carrying capacity of distributed photovoltaic access grid.
According to the announcement, Heilongjiang Development and Reform Commission has carried out the evaluation of the carrying capacity of distributed photovoltaic access grid in the whole province, and now the results of the evaluation of the carrying capacity of distributed photovoltaic access grid in the whole province will be announced by the end of November 2023. The results of the
announcement show that among the 125 counties (cities and districts) announced this time, there are 81 red grade areas, that is, the remaining network capacity of 81 places in the province is 0 , accounting for 65%.
Among them, the remaining network capacity of 14 counties (cities and districts) in Jiamusi City and Qihehe City is 0.
The original text is as follows:
Announcement
of Heilongjiang Development and Reform Commission on the Carrying Capacity of Distributed Photovoltaic Access Grid In order to promote the high-quality development of distributed photovoltaic, rationally arrange the scale and construction sequence of distributed photovoltaic filing, and guide the development and construction of distributed photovoltaic. The Commission organized the State Grid Heilongjiang Electric Power Company to carry out the evaluation of the carrying capacity of distributed photovoltaic access grid in the whole province, and now announces the results of the evaluation of the carrying capacity of distributed photovoltaic access grid in the whole province by the end of November 2023. Our committee will regularly publish the evaluation results of carrying capacity with Heilongjiang Electric Power Company of State Grid to guide the healthy and orderly development of distributed photovoltaic. Development and Reform Commission
of Heilongjiang Province December 25
, 2023 Attachment: Announcement
of Distributed Bearing Capacity at the End of November Note: 1. Green Grade Area. According to the capacity of distributed generation, we should promote the construction of distributed generation filing in an orderly manner.
2. Yellow grade area. Limited consumption of distributed generation grid connection, communication with local grid enterprises before filing of new distributed photovoltaic, and suspension of access to new distributed generation projects in areas where the reverse power flow of distribution network exceeds 80% of the equipment quota; Special analysis should be carried out for projects that really need to be connected in areas where the reverse power flow of distribution network does not exceed 80% of the equipment quota.
3. Red level area. It is difficult for distributed generation to connect to the grid . Before the carrying capacity of the grid is effectively improved, the filing of distributed generation projects will be suspended and the access of new distributed generation projects will be suspended.